Prior to the commencement of any works, the following requirements will be obtained from the main works contractor:Lifting permit and lifting plan to be completed and signed-off by (company) appointed person and supervised by the third-party certified and competent lifting supervisor during assembly.All lifting plants and equipment are certified by approved (municipality) Third-Party Testing Body. Lifting supervisor and rigger will inspect the lifting equipment prior to use and color-coded based on (company) safety color scheme for the current month.Third-party inspection and certification of the crawler crane after the function test to be submitted for review and records.Please note that you always ensure that procedure for assembly of crawler crane is perfectly followed.